Anthropic leases 191 MW from Bitcoin miner Riot

$9.1 billion over 20 years: Anthropic locks in Texas data center capacity as Riot pivots from mining to AI landlord.

Anthropic leases 191 MW from Bitcoin miner Riot
Illustration · AI-generated (AI IN LIFE)

In short

Anthropic has signed a long-term lease with Riot Platforms for 191 megawatts of data center capacity at Riot’s Rockdale, Texas campus.

At a glance

  • 191 MW of capacity at Riot’s Rockdale, Texas campus
  • Base value: $9.1B over 20 years, up to $16.5B with extensions
  • First 96 MW live from December 2027, full operation from June 2028
  • Bridge financing: $573M from Morgan Stanley
  • Riot’s stock jumped about 17% on the announcement

Anthropic has signed a long-term lease with Riot Platforms for 191 megawatts of data center capacity at Riot’s Rockdale, Texas campus. The base value is $9.1 billion over 20 years; with two optional five-year extensions, the deal could grow to as much as $16.5 billion, according to industry outlet DCD.

The timeline is ambitious: the first 96 megawatts are slated to go live in December 2027, with full commissioning planned for June 2028. The project is backed by a $573 million bridge financing facility from Morgan Stanley.

For Riot Platforms, the contract marks the next step in a remarkable transformation: the company, which grew up on Bitcoin mining, is increasingly positioning itself as a developer of large-scale data centers for AI and high-performance computing. Anthropic is the site’s second major tenant after AMD. Markets rewarded the deal – Riot’s stock jumped about 17 percent.

For Anthropic, the lease is another building block in the race for compute: frontier AI labs are locking in power and floor space at record pace, as training and inference demand outgrows what the traditional data center market can supply.

◈ AI-generated · sources linked

FAQ

What did Anthropic agree with Riot Platforms?

A 20-year lease for 191 megawatts of data center capacity in Rockdale, Texas, with a base value of $9.1 billion.

When does the capacity come online?

The first 96 megawatts are due in December 2027, with full operation planned for June 2028.

Why is a Bitcoin miner leasing to an AI lab?

Riot is transforming from a mining company into a developer of large data centers for AI and HPC – AI lab demand has become far more lucrative.