Anthropic leases 191 MW from Bitcoin miner Riot
$9.1 billion over 20 years: Anthropic locks in Texas data center capacity as Riot pivots from mining to AI landlord.

Illustration · AI-generated (AI IN LIFE)
At a glance
- 191 MW of capacity at Riot’s Rockdale, Texas campus
- Base value: $9.1B over 20 years, up to $16.5B with extensions
- First 96 MW live from December 2027, full operation from June 2028
- Bridge financing: $573M from Morgan Stanley
- Riot’s stock jumped about 17% on the announcement
Anthropic has signed a long-term lease with Riot Platforms for 191 megawatts of data center capacity at Riot’s Rockdale, Texas campus. The base value is $9.1 billion over 20 years; with two optional five-year extensions, the deal could grow to as much as $16.5 billion, according to industry outlet DCD.
The timeline is ambitious: the first 96 megawatts are slated to go live in December 2027, with full commissioning planned for June 2028. The project is backed by a $573 million bridge financing facility from Morgan Stanley.
For Riot Platforms, the contract marks the next step in a remarkable transformation: the company, which grew up on Bitcoin mining, is increasingly positioning itself as a developer of large-scale data centers for AI and high-performance computing. Anthropic is the site’s second major tenant after AMD. Markets rewarded the deal – Riot’s stock jumped about 17 percent.
For Anthropic, the lease is another building block in the race for compute: frontier AI labs are locking in power and floor space at record pace, as training and inference demand outgrows what the traditional data center market can supply.
FAQ
What did Anthropic agree with Riot Platforms?
A 20-year lease for 191 megawatts of data center capacity in Rockdale, Texas, with a base value of $9.1 billion.
When does the capacity come online?
The first 96 megawatts are due in December 2027, with full operation planned for June 2028.
Why is a Bitcoin miner leasing to an AI lab?
Riot is transforming from a mining company into a developer of large data centers for AI and HPC – AI lab demand has become far more lucrative.